South District Wastewater Treatment Plant

Odor Control Scrubber Buildings S0606 and S0608, Miami, Florida

Client

PCL Construction
1111 Park Centre Blvd, Suite 203 Miami, Florida 33169

Contact

Todd Palmatier
Email: TPalmatier@pcl.com
Phone: (305) 900-8911

Project Description

  • This project is one in a series of projects part of the Consent Decree. The project consists of furnishing all materials, labor, and equipment necessary for Odor Control Scrubber Buildings S0606 and S0608 upgrades.

Project Scope

  • The scope of work consists of furnishing all materials, labor, and equipment necessary for: Replacement of scrubber towers, sensors, ductwork, piping, gaskets, valves, brackets, hangers, recirculation pumps, scrubber fans, chemical storage tanks and feed pumps, chemical loading areas, and containment in the scrubber buildings.
  • Replace foul air ducts from Grit Chamber Building #2 to Scrubber Building S0608 and replace and install new foul air ducts from Grit Chamber Building #1 to Scrubber Building S0606.
  • Replacement of all odor control instrumentation and control, including new gas monitoring devices and fire detection alarms. Replacement of ventilation systems for Scrubber Buildings S0606 and S0608.

Project Cost

  • $ 580,554

Completion Date

  • October 2021