Upgrades to Sewage Pump Station No. 009

3071 SW 38 Avenue Miami, Florida 33146

Client

Miami-Dade Water & Sewer Department
3071 SW 38 Avenue Miami, Florida 33146

Contact

Isaac A. Gutierrez 
Pump Station Construction Supervisor

Phone: (786) 268-5173 

Project Description

  • The pump station remained in operation at all times while the rehabilitation was being executed by installing a temporary sewage by-pass system consisting of (3) 12” electric driven pumps with 18” suction and discharge piping. The project was completed ahead of schedule and within budget.

Project Scope

  • Installation of temporary sewage by-pass system and new 16” emergency pump-out systems. Demolition of existing pumps, pump motors, shafts, and piping systems. Removal of the sluice gate, electrical and control panels. Wet well rehabilitation.
  • Furnish and install three new 3150 GPM 60-HP vertical solids handling dry-pit sewage pumps with associated piping, valves, and fittings; new electrical equipment and pump level control panels. Installation of two hoist beams with 2 Ton trolleys.
  • New electrical duct bank. Installation of a new 7.5 kVA transformer and complete conduit and wiring terminations for connection to the existing RTU system.

Project Cost

  • $ 899,254

Completion Date

  • 2013